Stratford Coal Mine

Yancoal
  • >9,600Total workhours
  • >24,000M3Reclaim tunnel excavations
  • 7Induced fells
  • 4,680T | 145TFerrous & non ferrous steel recycled
  • Impacted Soil
  • Elevated Work Platforms
  • Mechanical Demolition
  • 3rd Party Engineering
  • Hot Works
  • Steel Recycling
  • Bulk Earthworks
  • Enviro Controls & Monitoring
  • Backfilling & Compaction
  • Site Establishment
  • Induced Collapse
  • Lead Contaminated Waste
  • 3D Engineered Model
  • Induced collapse and mechanical demolition methodologies for removal of various industrial structures – Train Loading Bin; Skyline Conveyors; Coal Processing Plant & Ultra Fines Building; Transfer & Tipper Tower; Reclaim Tunnels; ROM Bin & Wall; Light Tower; and Train Parking Bay
  • Site specific work plans designed to accommodate unique safety and environmental attributes for successful execution of induced fells and tunnel excavations
  • Demolition of two Reclaim Tunnels (90m and 140m long) required extensive excavations, heavily reinforced concrete removal, and careful management of contaminated materials
  • Induced collapse of major structures (up to 35m high) involved strict wind limits, complex pre-cut sequencing, unstable ground conditions, and restricted access for 120T excavator
  • Demolition works adjacent to 11kV live services required strict isolation procedures, enhanced safety controls, and spotter supervision