Two Mile Infrastructure
Rio Tinto
- >2,500Total workhours
- >600TConcrete & steel recycled
- Asset Recovery & Salvage
- Mechanical Demolition
- Elevated Work Platforms
- Hot Works
- Saw Cutting
- 3rd Party Engineering
- Enviro Controls & Monitoring
- Concrete Recycling
- Steel Recycling
- Industrial Waste Transport
- Validation testing
- Site Establishment
Unique Attributes
- Remobilise people and plant to remote site in The Pilbara region of Western Australia after 11 month hold on project
- Demolition of multiple structures – Flash Butt Welding Facility (and associated infrastructure); Overhead Gantry Crane; RSM Workshop frame; and workforce amenities structure
- Design and construction of a sorting platform to palletise rail sleepers
Key Challenges
- Isolation and relocation of electrical services
- Loading and removal of 800 (heavy metal) contaminated wooden rail sleepers
- Removal of 17 Rail Gantries (suspended over rail tracks)
- Demolition of a 27 tonne Butt Welder structures
- Demolition of Workshop frame adjacent to office structures
- Relocation of demountable office structure
×![]()